You can save and copy revenue planning in individual plan versions and analyze the different versions using reports in the project information system. You can change values planned manually in all plan versions in parallel. You can then compare alternative plans, for example, a best-case scenario with a worst-case scenario.
When you create a controlling area, the system automatically creates a plan version (000) for planned/actual values. The actual values are posted in this version.
Define Controlling Versions
For Easy Cost Planning, you can define the controlling version for planning calculated values. In the standard system, you can find the update of the calculated values from Easy Cost Planning in controlling version 000.
You can also define if Easy Cost Planning is used to plan revenue.
You can define the controlling versions you want available in Easy Cost Planning for each controlling area. You must also specify the leading controlling version again in the alternative version table.
Optionally, you can specify a costing variant for each controlling version. If you perform this action, the system automatically uses this costing variant in the controlling version when you perform cost planning in Easy Cost Planning. If you do not specify a costing variant, you must specify it once per project/version when you perform cost planning in Easy Cost Planning.