Planned Costs

Knowledge quiz

It's time to put what you've learned to the test, get 8 right to pass this unit.

1.

What interfaces are available with cost planning in SAP S/4HANA?

There are two correct answers.
2.

Only a primary cost element can be assigned to the process master record.

Choose the correct answer.
3.

You can access Easy Cost Planning for projects in the Project Builder when the system has been configured to use this feature with network activities.

Choose the correct answer.
4.

The statistical key figure determines if planned costs are calculated for the activity.

Choose the correct answer.
5.

For which of the following items can you determine planned costs?

There are four correct answers.
6.

You can plan travel expenses using general cost activities.

Choose the correct answer.
7.

Cost planning using unit costing is period based.

Choose the correct answer.
8.

Which of the following factors should you consider when specifying theAppended and Apportioned indicators?

There are three correct answers.
9.

Project scheduling and cost element planning are independent of each other.

Choose the correct answer.
10.

You can change the costing sheet and overhead key in the activity-assigned header.

Choose the correct answer.