The system valuates the planned quantities of the material components using the material list.
The system determines the planned activity quantities using the master recipe. To valuate the planned material components, activities, and business processes, the system uses the planned valuation variant specified in the default values for the order type/plant combination. The system calculates the overhead costs using the costing sheet specified in the planned valuation variant.
If template allocation is being used, the template which is used must be assigned to the following:
Controlling Area
Environment, for and production orders environment 001.
Controlling Area
Environment
Costing Sheet
Overhead Key
The order costs are actually calculated on the order header. A preliminary cost estimate could be generated automatically for the production order when it is saved or released, in accordance with the Customizing settings in the default values for the order type, together with the plant.