Controlling Object Cost
Controlling Product Cost by Period
Controlling Product Cost by Period for Period-End Closing
Controlling Product Cost by Orde
Controlling Product Cost by Order for Period-End Closing
Exploring Sales-Order-Related Production Scenarios in Cost Object Controlling
Controlling Product Cost by Sales Order with Production
Configuring Product Cost Controlling by Sales Order
Controlling Product Cost by Sales Order for Period-End Closing
Controlling Product Cost by Sales Order without Production (Service)
Understanding Information Systems for Product Cost Controlling

Performing Template Allocation

Objective

After completing this lesson, you will be able to perform template allocation

Template Allocation

The image shows an allocation of product cost from a standard cost estimate for 10 units to a product cost collector for 2 delivered units, highlighting the changes in quality check and transport costs.

Template allocation is a technique for transferring the costs of Overhead Cost Controlling to other Controlling objects on the basis of consumption. All Controlling objects are suitable for use as receivers, especially cost objects.

Note

In SAP S/4HANA release 1610, the template allocation to CO PA is not available.

The template allocation technique allocates processes of Activity-Based Costing (CO-OM-ABC) with the help of activity types from cost center to other controlling objects.

The process template is determined dynamically based on the following parameters:

  • The system selects the costing sheet for the application of overhead with the valuation variant.

  • You can either enter the overhead key directly in the cost object or derive it from the overhead group from the material master (costing 1 view).

  • You can assign a template in Customizing with the combination of overhead key and costing sheet.

You must define a template in which you use the function ORDER_TARGET_PROCESS_QUANTITY to calculate the actual process quantity. This function allows the system to calculate target costs of the process on the basis of the current standard costs.

Perform Template Allocation

Summary

  • Template allocation transfers overhead costs to other controlling objects based on consumption.
  • It allocates processes with activity types from cost centers to cost objects.
  • Costing sheet and overhead key determine template allocation.
  • Template allocation technique uses diverse cost drivers.