Customizing in Time Scheduling

Objective

After completing this lesson, you will be able to customize in time scheduling

Customization Settings for Time Scheduling

Scheduling Parameter Indicators

Scheduling parameters are created for specific plants and network types. The scheduling parameters determine scheduling, for example, in the transactions network maintenance (CN22) and scheduling of the overall network (CN24). The indicators have the following meanings:

Customizing for Scheduling 2

Screenshot of the Parameters for WBS scheduling settings window, featuring options for scheduling type, form, reduction parameters, and other customizable checkboxes.

The profile for WBS scheduling is used for scheduling in the project planning board transaction (CJ2B) or in the project scheduling transaction (CJ29).

The indicators have the following meanings:

Scheduling Type

Determines the type of scheduling, for example, forward first, then backward.

Start in the past

Determines how long ago (in days) the start date can be. If it is more than the specified number of days, scheduling is carried out for today’s date.

Scheduling form

Specifies which object - network header or WBS element - is used as a basis for scheduling.

Adjust basic dates

Determines that the scheduled dates are copied to the basic dates of the WBS elements after a scheduling run.

Log automatic

If a log is generated, it is displayed automatically.

Shift order

Determines how the system deals with partially confirmed activities during scheduling.

Schedule when saving

Scheduling is carried out on saving.

Latest material dates

The requirements dates for a material are determined based on the earliest or latest date.

Maximum reduction level

A reduction strategy can have up to six levels. The highest level of reduction is specified here.

Reduction Type

The activity duration is reduced for either all activities or only those along the critical path are reduced.

The WBS scheduling profile is stored in the project definition control data. It can be copied as a default value from the project profile. One (or neither) of the two scheduling scenarios is displayed by default in the project profile.

How to Customize in Time Scheduling