Knowledge quiz

It's time to put what you've learned to the test, get 8 right to pass this unit.

1.

If Bottom-up is selected as the scheduling scenario, what happens to the activity dates?

Choose the correct answer.
2.

Activity elements are scheduled independently of the higher-level activity.

Choose the correct answer.
3.

The Shift order indicator controls how actual dates from final confirmations affect further scheduling runs.

Choose the correct answer.
4.

Which factors can have an influence on the scheduling result of networks?

There are five correct answers.
5.

The system automatically calculates the actual dates for a WBS element from the accounting documents assigned to the WBS element.

Choose the correct answer.
6.

The scheduling type determines the original direction in which scheduling is carried out. Networks are always scheduled forwards and backwards.

Choose the correct answer.
7.

The free float is the difference between the earliest finish date for an activity and the earliest start date for the successor.

Choose the correct answer.
8.

WBS elements can be linked together using relationships in order to specify the chronological order of WBS elements.

Choose the correct answer.
9.

The system carries out check available capacities when using the reduction function.

Choose the correct answer.
10.

The system determines the order of FS relationships based on how activities are displayed in the planning board (from top to bottom).

Choose the correct answer.