You use activities in the network to plan the resources required for a project.
The Project System distinguishes the following resources:
An internally processed activity defines the output to be provided by machines and/or personnel of the actual company to complete the activity. You can evaluate the capacity load utilization of the work centers involved, schedule these capacities as necessary, and distribute work among employees.
You use an externally processed activity to specify the services that need to be provided by other companies to complete the activity. The Purchasing Department is responsible for the purchasing of external work.
Service activities are also used to procure services externally. In contrast to externally processed activities, service activities allow you to draw up service specifications and enter value limits for any unplanned services. The purchase of the required services along with the entry and acceptance of the services performed is also carried out by the Purchasing Department.
External Activity Detail Screen

In the preceding figure, the data for the external activity was read from a purchasing info-record. The fields read, for example the price per unit, are referenced, which means that changes are no longer allowed in the activity.