Logistics Projects Overview
Functions and Types of Scheduling
Project Capacities
External Activities
Project Materials
Project-Oriented Procurement Analysis
Workflows in Project System
Progress Tracking

Setting Actual Dates for WBS Elements and Activities

Objectives

After completing this lesson, you will be able to:
  • Enter actual dates for WBS elements
  • Enter actual dates for network activities

Actual Dates

Note

Actual dates are usually updated for an activity during activity confirmation. You can suppress this update if necessary. To do this, select the No date update indicator during confirmation.

Actual Dates of WBS Elements

AS = Actual start dateAF= Actual finish date
CNF= Finally confirmedREL= Released

How to Enter Actual Dates for WBS Elements

Enter Actual Dates for WBS Elements

Actual Dates of Activities

Enter Actual Dates for Network Activities