Actual Dates

Note

Actual dates are usually updated for an activity during activity confirmation. You can suppress this update if necessary. To do this, select the No date update indicator during confirmation.

Actual Dates of WBS Elements

AS = Actual start dateAF= Actual finish date
CNF= Finally confirmedREL= Released

How to Enter Actual Dates for WBS Elements

Enter Actual Dates for WBS Elements

Actual Dates of Activities

Enter Actual Dates for Network Activities