Material for the Production Order
Editing the Production Order

The final confirmation is entered for the production order and material P-FL300 is delivered to the project stock.
This increases the stock quantity and value for material P-FL300 in the project stock. The total value of the increased inventory is the quantity received times the standard cost.
A goods issue is posted for the network for the consumption of the assembly P-FL300.
This reduces the project stock (crediting the WBS element). The actual costs are debited from the network.
The actual network activity costs are aggregated and displayed for the higher-level WBS elements.