
Each time a network is scheduled, the system carries out forward and backward scheduling and determines floats and capacity requirements (if activated), as follows:
Forward scheduling determines the earliest dates.
Backward scheduling determines the latest dates.
Scheduling
WBS / Overall Network Scheduling
The activity data, relationships between the activities, and date restrictions, form the basis for determining dates automatically (scheduling).
As of Release 4.6A, you can schedule maintenance orders from the Project System. In the Project Scheduling and Overall Network Scheduling transactions, you can specify whether networks are scheduled together with maintenance orders that have been assigned as subnetworks.
You can display an overview of the maintenance orders assigned to a project in the project planning board.
