Logistics Projects Overview
Functions and Types of Scheduling
Project Capacities
External Activities
Project Materials
Project-Oriented Procurement Analysis
Workflows in Project System
Progress Tracking

Knowledge quiz

It's time to put what you've learned to the test, get 8 right to pass this unit.

1.

In the Project System, only personnel resources represent capacities.

Choose the correct answer.
2.

If you want to distribute work to persons in a project organization for a certain project, you need to assign this project organization for all WBS elements of the project.

Choose the correct answer.
3.

Which options are available for confirmations of network activities in the Project System?

There are five correct answers.
4.

Which two of the following key settings influence the calculation of capacity requirement?

There are two correct answers.
5.

Data entry profiles allow the user to define the layouts and different functions of CATS.

Choose the correct answer.
6.

Which of the following prerequisites need to be met to analyze the capacity requirements of an activity?

There are four correct answers.
7.

The tabular capacity planning board can be called up in which of the following views?

There are three correct answers.
8.

With collective confirmation, you can simultaneously confirm the following: various networks, activities, activity elements, and individual capacities.

Choose the correct answer.
9.

On the Capacity Planning: Standard Overview screen, which menu path finds all capacity requirements for your project?

Choose the correct answer.
10.

In the capacity reports for the Structures Information System, all requirements are displayed for the resources selected.

Choose the correct answer.