Processing Internal Activities

Objective

After completing this lesson, you will be able to process internal activities

Lifecycle of Internal Activities

Diagram titled Overview of Capacities showing connections for internal activity (100 H work) to progress, structure, bottlenecks/comparison, work center, machines, and more.

The planning of internal activities has a considerable influence on other objects and aspects in the Project System and in Capacity Planning.

Lifecycle of an Internal Activity

Internal Processing in the Project Planning Board

A project planning board displaying tasks with steps: 1) Create activity, 2) Generate capacity requirements, 3) Evaluate capacity, 4) Release activity, 5) Confirm activity.

You can use the project planning board to carry out all steps involved in the processing of internal activities.

The preceding figure shows only the minimum processing procedure. You can also call up workforce planning and capacity leveling directly from the planning board.

Process Internal Activities